If a power-off drill is required due to customer requirements
null
please pay attention to:
1) Please try to ensure that the power-off drill test is carried out under remote disaster recovery conditions, and the business can be taken over in time in case of an unexpected situation
2) Backup the license file, configuration file and map file
3) In order to prevent unexpected situations, it is best for the customer to have redundant equipment on site, so that the business can be taken over in time in case of unexpected situations
4) Collect a device diagnostic before powering down. for comparison after the device reboot is complete
5) Make a complete record of the power-off drill process. Record each operation and the corresponding operation time node
6) Confirm the customer's license authorization code (the authorization serial number on the "Software Authorization Letter"), the device SN
7) In order to prevent accidents, please apply for a corresponding number of temporary licenses in advance to restore business in time
For more drill notes, please pay attention to the case: